CEC Commissions $125.8M USD Itimpi II Solar Plant
Copperbelt Energy Corporation has commissioned the 136 MW Itimpi II Solar Plant in Zambia, increasing its total installed solar capacity from 94 MW to 230 MW. The Solar Plant is now the largest operational solar facility in Zambia and among the largest in sub-Saharan Africa.
The project was delivered over a 14-month period at a total cost of USD 125.8 million (ZMW 3.1 billion) and was financed through Copperbelt Energy Corporation’s USD 200 million Green Bond. The use of domestic capital markets to fund the development highlights an alternative financing pathway for large-scale energy infrastructure, reducing reliance on sovereign borrowing and external funding sources.
The Itimpi II Solar Plant adds significant generation capacity to Zambia’s power system, supporting efforts to diversify the energy mix away from hydropower. The country has faced ongoing challenges linked to hydrological variability, making the addition of solar capacity increasingly relevant for improving supply stability and reducing seasonal risks.
At the commissioning event held on Thursday, 30 April 2026, Republican President Hakainde Hichilema positioned the project within Zambia’s broader energy strategy, highlighting the risks of the country’s historical dependence on hydropower and the urgent need to accelerate investment in alternative energy sources.
“This is a great day and another very important project that contributes directly to our objective of increasing electricity generation in Zambia,” he said. The President emphasised that diversification was no longer optional, but necessary for economic growth and export competitiveness. He reiterated the Government’s support for private sector participation, stating directly to developers: “You have our full support not partial support, but full support.”
CEC PLC Board Chairperson London Mwafulilwa said the commissioning of the plant was a bold statement that Zambia is ready, capable, and committed to driving progress through investment, partnership, and decisive action. “The project reflected real impact beyond infrastructure, and the Group remained committed to investing in the future, working with Government, communities, investors, and partners to build a stronger and more resilient nation,” he added.
For CEC PLC Chief Executive Officer Owen Silavwe, the achievement is a story of national empowerment. “Thousands of Zambians contributed their skills, effort, and dedication to bring this project to life, turning ambition into a landmark of national progress,” he stated, noting that Itimpi II is part of a broader commitment to expanding renewable energy and delivering sustainable power for long-term economic development.
Partners also weighed in on the broader implications. Securities and Exchange Commission Chief Executive Officer Philip Chitalu noted that CEC surpassed a US$100 million national capital markets target by raising US$156 million, demonstrating the power of local markets to fund national development.
Stanbic Bank Zambia Chief Executive Officer Mwindwa Siakalima commended CEC’s role in securing critical power supply, while Public Private Dialogue Forum (PPDF) Acting Deputy Director General Jacquiline Chishimba applauded the project for directly hitting national targets for job creation, wealth creation, and skills transfer.
From generation to dispatchable power, the meaning of this investment extends well into the future. By 2027, the Group intends to have more than 500 MW of solar generation capacity.
Project
| Name | Itimpi Solar Plant: Phase 2 |
| Country | Zambia |
| Status | Commissioned |
Organizations Involved
Track every solar plant in Zambia
123 plants · 132 companies
The developer, investor, lender, offtaker and EPC on each plant, which roles are still open, and what changed this month. $89 every 3 months.