Mauritania Signs $300M Agreement for 160 MW Solar Plant with Storage
Mauritania has taken a major step in its clean energy transition by signing a $300 million agreement with Ewa Green Energy to build a 220 MW hybrid power facility, anchored by a 160 MW solar PV plant combined with a 370 MWh battery energy storage system (BESS).
The agreement, signed on September 12, 2025 in Nouakchott, marks Mauritania’s first large-scale public-private partnership (PPP) for renewable power. The project will be developed under a build-operate-transfer (BOT) structure, with electricity to be sold to the state utility SOMELEC through a long-term power purchase agreement.
The core of the project is solar. With 160 MW of photovoltaic capacity, the facility will represent one of the largest solar plants in West Africa once commissioned. The solar park will be complemented by 60 MW of wind power and paired with large-scale storage, enabling the plant to deliver firm and reliable renewable electricity to the grid.
By relying primarily on solar energy, the initiative is expected to significantly reduce Mauritania’s dependence on imported fuels, cut generation costs, and provide clean electricity to both urban and rural communities. The project represents a total investment of about USD 300 million. Ewa Green Energy, backed by international investors, will develop, finance, build, and operate the facility until it is transferred to the government at the end of the concession period.
Construction is set to begin shortly, with completion targeted for September 2026. Once operational, the plant will contribute to Mauritania’s goal of achieving universal electricity access and increasing the share of renewables in its national energy mix. Government officials hailed the deal as a milestone in the country’s energy strategy. The hybrid design, combining solar with wind and storage, will strengthen grid stability and ensure round-the-clock availability of power, key for supporting industrial growth and improving living standards.
Project
| Name | Nouakchott Solar Plant |
| Country | Mauritania |
| Status | Planning |
Organizations Involved
Track every solar plant in Mauritania
42 plants · 5 companies
The developer, investor, lender, offtaker and EPC on each plant, which roles are still open, and what changed this month. $89 every 3 months.