Niger Commissions 30 MW Gorou Banda Solar Plant
The 30 MW Solar Plant has been commissioned with total financing of approximately USD 33 million (CFA 20 billion).
The facility, which consists of more than 55,000 solar panels, is currently the largest solar power installation in Niger. According to Niger’s Energy Minister, Mahaman Moustapha Barké, the national utility Nigelec has already begun to observe improvements in electricity service quality for customers, particularly in Niamey, as well as in Dosso in the south and Tillabéri in the west.
However, the commissioning process faced delays after most expatriate technical staff left the country following the July coup. Officials stated that the project was ultimately completed with the support of remaining technicians based in Niamey. The plant was originally inaugurated by former President Mohamed Bazoum together with EU foreign policy chief Josep Borrell. The French embassy later noted that, due to the altered completion conditions, the plant may still face certain operational risks.
The total project cost stands at about USD 33 million (CFA 20 billion), financed through a USD 25.5 million loan from the French Development Agency and a USD 5.7 million grant from the European Union.
The project was developed to help address electricity shortages after Nigeria suspended power exports to Niger following ECOWAS sanctions. Prior to the disruption, Nigeria supplied around 70% of Nigelec’s electricity imports, making the new solar facility a critical source of domestic generation capacity.
Project
| Name | Gorou Banda Solar Plant |
| Country | Niger |
| Status | Planning |
Organizations Involved
Track every solar plant in Niger
30 plants · 18 companies
The developer, investor, lender, offtaker and EPC on each plant, which roles are still open, and what changed this month. $89 every 3 months.